Our experience includes some relevant projects,
![1_ULLUM SOLAR I, II, III_100 MWp_SAN JUAN_ARGENTINA_GENNEIA](https://erp-energy.com/wp-content/uploads/2021/05/1_ULLUM-SOLAR-I-II-III_100-MWp_SAN-JUAN_ARGENTINA_GENNEIA.jpg)
Ullum I-II-III solar plant
Country: San Juan, Argentina
80 MW
Services: Owner’s Engineering
Description:
ERP reviewed the detailed engineering of the three power plants built simultaneously and assigned an on-site team to oversee the construction and commissioning of the project for the Argentinian utility company GENNEIA. ERP also carried out a detailed review of the static and dynamic design of the solar tracking system provided by ARRAY.
![2_CALDENES DEL OESTE SOLAR_30 MWp_SAN LUIS_ARGENTINA_TOTAL EREN](https://erp-energy.com/wp-content/uploads/2021/05/2_CALDENES-DEL-OESTE-SOLAR_30-MWp_SAN-LUIS_ARGENTINA_TOTAL-EREN.jpg)
Caldenes del Oeste solar plant
Country: San Luis, Argentina
25 MW
Services: Owner’s Engineering
Description:
ERP reviewed the detailed engineering of the plant and assigned an on-site team to supervise the construction and commissioning of the project for the French IPP EREN. ERP also carried out a detailed review of the static and dynamic design of the solar tracking system provided by CONVERT.
![3_SOL DE SANTA INES_30 MW_BIO BIO_CHILE_SUNGROW](https://erp-energy.com/wp-content/uploads/2021/05/3_SOL-DE-SANTA-INES_30-MW_BIO-BIO_CHILE_SUNGROW.jpg)
Sol de Santa Inés solar plant
Country: Bio Bio, Chile
3 MW
Services: Owner’s Engineering
Description:
ERP developed the basic engineering, power production reports, RFP for the EPC bidding process and supported the MSA contract for the Chinese-headquartered Company SUNGROW. ERP also reviewed the detail engineering of the plant (and construction engineering after completion) and assigned an on-site team to oversee the construction and commissioning of the project.
![4_CENTRAL EOLICA PAMPA DE MALASPINA_50 MW_CHUBUT_ARGENTINA_TOTAL EREN](https://erp-energy.com/wp-content/uploads/2021/05/4_CENTRAL-EOLICA-PAMPA-DE-MALASPINA_50-MW_CHUBUT_ARGENTINA_TOTAL-EREN.jpg)
Malaspina Wind Farm
Country: Chubut, Argentina
50 MW
Services: EPC-M Construction Management
Description:
Following the acquisition by the French-headquartered Company TOTAL EREN of the full EPC contract following its early termination with SENVION, ERP provided an on-site team of 10 experienced people to supervise construction activities, ensure compliance with contractual obligations and verify quality of the works and the start. -up of the project. ERP also performed procurement and logistics tasks, specific project planning work, document control, and review of quality control and quality assurance programs.
![5_CENTRAL EOLICA VIENTOS LOS HERCULES_100 MW_SANTA CRUZ_ARGENTINA_TOTAL EREN](https://erp-energy.com/wp-content/uploads/2021/05/5_CENTRAL-EOLICA-VIENTOS-LOS-HERCULES_100-MW_SANTA-CRUZ_ARGENTINA_TOTAL-EREN.jpg)
Los Hércules Wind Farm
Country: Santa Cruz, Argentina
92,7 MW
Services: EPC-M Construction Management
Description:
Following the acquisition by the French Japanese consortium TOTAL EREN-MITSUI of the full EPC contract after its early termination with SENVION, ERP provided an on-site team of 13 experienced people to supervise construction activities, ensure compliance with contractual obligations and verify the quality of the works and the implementation of the project. ERP also performed procurement and logistics tasks, specific project planning work, document control, and review of quality control and quality assurance programs.
![6_CENTRAL EOLICA ARAUCO ETAPAS 1-2_100 MW_LA RIOJA_ARGENTINA_PARQUE EOLICO ARAUCO SAPEM](https://erp-energy.com/wp-content/uploads/2021/05/6_CENTRAL-EOLICA-ARAUCO-ETAPAS-1-2_100-MW_LA-RIOJA_ARGENTINA_PARQUE-EOLICO-ARAUCO-SAPEM.jpg)
Arauco II, Etapas 1-2 Wind Farm
Country: La Rioja, Argentina
100 MW
Services: Owner’s Engineering
Description:
ERP acted as Owner Engineer of the electricity company of the Government of the Province of La Rioja and assigned an on-site team to supervise the construction and start-up of the project.
![7_CAFAYATE SOLAR_100 MWp_SALTA_ARGENTINA_CANADIAN SOLAR](https://erp-energy.com/wp-content/uploads/2021/05/7_CAFAYATE-SOLAR_100-MWp_SALTA_ARGENTINA_CANADIAN-SOLAR.jpg)
Cafayate solar plant
Country: Salta, Argentina
80 MW
Services: Owner’s Engineering
Description:
ERP acted as Owner’s Engineer for CANADIAN SOLAR. ERP also reviewed the detail engineering of the plant and assigned an in-situ team to supervise the construction and commissioning of the project. ERP also carried out quality control inspections of the Works with an extra assigned in-situ team. ERP also provided detailed static and dynamic design review of the solar tracker system provided by CONVERT.
![8_IGLESIA-GUAÑIZUIL SOLAR_80 MWp_SAN JUAN_ARGENTINA_JINKO POWER](https://erp-energy.com/wp-content/uploads/2021/05/8_IGLESIA-GUAÑIZUIL-SOLAR_80-MWp_SAN-JUAN_ARGENTINA_JINKO-POWER.jpg)
Iglesia-Guañizuil solar plant
Country: San Juan, Argentina
80 MW
Services: Asset Manager
Description:
ERP acts as Asset Manager for JINKO SOLAR in a long-term agreement, supervising the O&M Works performed by Sterling and Wilson including weekly site visits.
![9_ARAUCANIA WIND FARM_DUE DILIGENCE._EDF](https://erp-energy.com/wp-content/uploads/2021/05/9_ARAUCANIA-WIND-FARM_DUE-DILIGENCE._EDF.jpg)
La Araucania wind farm (confidential)
Country: La Araucania, Chile
150 MW
Services: Due Diligence
Description:
ERP carried out a technical due diligence for the potential acquisition of a wind farm in Chile for French-headquartered company EDF.
![10_LA RIOJA SOLAR POWER PLANT_DUE DILIGENCE._EDF](https://erp-energy.com/wp-content/uploads/2021/05/10_LA-RIOJA-SOLAR-POWER-PLANT_DUE-DILIGENCE._EDF.jpg)
Nonogasta Solar Plant
Country: La Rioja, Argentina
40 MW
Services: Due Diligence
Description:
ERP carried out a technical due diligence for the potential acquisition of a solar plant in Argentina for TOTAL EREN.
![11_SAN MIGUEL_50 MW_PROJECT DEVELOPMENT_SAN LUIS_ARGENTINA_MOLINO CAÑUELAS](https://erp-energy.com/wp-content/uploads/2021/05/11_SAN-MIGUEL_50-MW_PROJECT-DEVELOPMENT_SAN-LUIS_ARGENTINA_MOLINO-CAÑUELAS.jpg)
San Miguel Solar Plant
Country: San Luis, Argentina
50 MW
Services: Greenfield Project Development
Description:
ERP carried out the full permitting of the solar project “from the scratch” achieving the ready-to-bid status, including the completion of feasibility studies, basic engineering, environmental impact assessment, geotechnical studies campaigns, topographical surveys, and electrical studies (transitory status, short-circuit status, and load flow modelling) for the Argentine-headquartered company MOLINO CAÑUELAS.
![13_CRUCE DEL TOCOTA_100 MW_PROJECT DEVELOPMENT_SAN JUAN_ARGENTINA_SUNCO](https://erp-energy.com/wp-content/uploads/2021/05/13_CRUCE-DEL-TOCOTA_100-MW_PROJECT-DEVELOPMENT_SAN-JUAN_ARGENTINA_SUNCO.jpg)
Retamal Solar Plant
Country: San Juan, Argentina
100 MW
Services: Greenfield Project Development
Description:
ERP carried out the full permitting of the solar project “from the scratch” achieving the ready-to-bid status, including the completion of feasibility studies, basic engineering, environmental impact assessment, geotechnical studies campaigns, topographical surveys, and electrical studies (transitory status, short-circuit status, and load flow modelling) for the Spanish-headquartered company SUNCO.
![13_CRUCE DEL TOCOTA_100 MW_PROJECT DEVELOPMENT_SAN JUAN_ARGENTINA_SUNCO](https://erp-energy.com/wp-content/uploads/2021/05/13_CRUCE-DEL-TOCOTA_100-MW_PROJECT-DEVELOPMENT_SAN-JUAN_ARGENTINA_SUNCO.jpg)
Cruce del Tocota Solar Plant
Country: San Juan, Argentina
100 MW
Services: Greenfield Project Development
Description:
ERP carried out the full permitting of the solar project “from the scratch” achieving the ready-to-bid status, including the completion of feasibility studies, basic engineering, environmental impact assessment, geotechnical studies campaigns, topographical surveys, and electrical studies (transitory status, short-circuit status, and load flow modelling) for the Spanish-headquartered company SUNCO.
![](https://erp-energy.com/wp-content/uploads/2021/02/MapaBeig.png)
CHILE OFFICE
Cerro el Plomo 5420
Las Condes, Santiago (Chile)
chile@erp-energy.com
ARGENTINA OFFICE
Av. Alicia M. De Justo 1848
Puerto Madero, Buenos Aires
(Argentina)
argentina@erp-energy-com